Rajasthan OSHWC Rules, 2026 · Rule 72

Rule 72: Intimation of work order and time limit for intimation under section 50

Explains the operative legal effect of intimation of work order and time limit for intimation under section 50 under the 2026 Scheme, including who must act, what conditions apply and how the paragraph interacts with the Code on Social Security, 2020.

Final State RuleS.O. 23Effective 30 Jun 2026

Finin2min summary

Explains the operative legal effect of intimation of work order and time limit for intimation under section 50 under the 2026 Scheme, including who must act, what conditions apply and how the paragraph interacts with the Code on Social Security, 2020.

Jurisdiction: Rajasthan. These are final State rules notified under sections 133 and 135 of the OSHWC Code, 2020 and are not interchangeable with Central or another State's rules.

Full notified Rule text

72. Intimation of work order and time limit for intimation under section 50.- (1) Every contractor shall within fifteen days of the receipt of a contract work order shall intimate about the contract work order containing the details such as the name of the principal employer, address of the premises where work is being undertaken, date of commencement of the contract work, the number of contract labour employed under that work order, duration of work orders. (2) the details of work order shall be sent by the contractor or his authorized representative. (3) The intimation shall be sent electronically on the Official Portal or e-mail of the Labour Commissioner or his representative as may be notified on the website of Labour Department.

Official Rajasthan Gazette - S.O. 23

Clause / sub-rule explanation

(1)

(1) Every contractor shall within fifteen days of the receipt of a contract work order shall intimate about the contract work order containing the details such as the name of the principal employer, address of the premises where work is being undertaken, date of commencement of the contract work, the number of contract labour employed under that work order, duration of work orders.

Explanation: This sub-rule/clause must be applied with the rule heading, definitions and any linked Code provision. Check whether a prescribed form, authority or threshold is triggered.

(2)

(2) the details of work order shall be sent by the contractor or his authorized representative.

Explanation: This sub-rule/clause must be applied with the rule heading, definitions and any linked Code provision. Check whether a prescribed form, authority or threshold is triggered.

(3)

(3) The intimation shall be sent electronically on the Official Portal or e-mail of the Labour Commissioner or his representative as may be notified on the website of Labour Department.

Explanation: This sub-rule/clause must be applied with the rule heading, definitions and any linked Code provision. Check whether a prescribed form, authority or threshold is triggered.

Thresholds / timelines found

No standalone numeric threshold extracted; apply the qualitative conditions and linked schedules/forms.

Practical example

A compliance team facing a 'Intimation of work order and time limit for intimation under section 50' event should identify the statutory trigger, responsible actor and documentary evidence from this paragraph before filing, paying, approving or rejecting the transaction.

Q&A

What does Rajasthan Rule 72 cover?

Explains the operative legal effect of intimation of work order and time limit for intimation under section 50 under the 2026 Scheme, including who must act, what conditions apply and how the paragraph interacts with the Code on Social Security, 2020.

Does this Rule apply outside Rajasthan?

No. This page explains the final Rajasthan State rule. Other States/UTs may have different final, draft or saved rules.

What should an employer verify before acting?

Confirm applicability under the OSHWC Code, read this Rule with its definitions/schedules/forms, verify the current Rajasthan Gazette and retain evidence of compliance.