FININ2MIN · JUDGMENT INTELLIGENCE
Insolvency & IBC · F2J-C-4133

Satinder Singh Bhasin v. Government of NCT of Delhi & Ors

Conditions of bail that a developer settle with all complainants, by delivering units with clear title or refunding money, within six to eight months, are conditions on which his liberty depends, and he must show bona fide efforts to comply; where the project is incomplete and unfit for possession, no settlement by possession is possible, so non-payment of statutory dues to the authority, failure to execute tripartite sublease deeds, and non-settlement over years show non-compliance; transfers of funds from a corporate debtor to related entities after admission to CIRP, despite the moratorium and the NCLAT's status quo order, are not consistent with bail conditions; and the forfeiture clause allows the Court to forfeit the deposit in full.

By CA Nikhil Gupta · Reviewed against the retained judgment 2026-10-06

Finin2min two-minute summary

Homebuyers of Bhasin Infotech's Grand Venice project, who had paid for units that were never made ready, asked the Supreme Court to cancel the bail granted to its promoter, Satinder Singh Bhasin, as he had not settled their claims. The Court cancelled the bail and forfeited the Rs. 50 crores he had deposited.

Court
Supreme Court of India
Case
Miscellaneous Application No. 239 of 2024 in Writ Petition (Crl.) No. 242 of 2019
Date
2026-04-02
Bench
Sanjay Karol, Nongmeikapam Kotiswar Singh
Subject
Banking, Insolvency and Finance
Disposition
Applications allowed; bail granted on 6 November 2019 to the Grand Venice promoter cancelled, Rs. 50 crores deposit forfeited and passport to stay with the Court
Result
The batch of Miscellaneous Applications of allottees of the Grand Venice project in M.A. No. 239 of 2024 in W.P. (Crl.) No. 242 of 2019 was allowed, the bail granted on 6 November 2019 was cancelled with an order to surrender within one week, the petitioner was left free to apply for regular bail afresh after twelve months subject to full compliance with the orders in the insolvency proceedings, the Rs. 50 crores deposited with its accrued interest was forfeited, of which Rs. 5 crores with interest went to the National Legal Services Authority and the rest to the IRP, and his passport was not to be released without leave of the Court.
Neutral citation
2026 INSC 310
CNR
Not stated in retained copy
Connected matters
None recorded
Relevant period
See facts and judgment
Read complete judgment PDFPublic court copyOfficial court portal

What happened

Satinder Singh Bhasin, the then Director of Bhasin Infotech and Infrastructure Private Limited (BIIPL), filed W.P. (Crl.) No. 242 of 2019 under Article 32 for clubbing of the FIRs filed in Delhi and Uttar Pradesh by allottees of the Grand Venice project, and by order of 6 November 2019 the Supreme Court granted him bail on conditions that he would not commit a similar offence, would deposit Rs 50,00,00,000 as a pre-condition, and would settle with every complainant within six to eight months as ordered by the Patiala House Court on 15 May 2019, failing which no less than 50% of the deposit would be forfeited. The Court refused to waive the deposit on 25 November 2019. Allottees then moved applications for cancellation. The NCLT admitted the company petition of allottees against BIIPL and Grand Venice Commercial Tower Private Limited (GVCTPL) and appointed an IRP; GVCTPL was admitted on 4 December 2023, with the NCLAT's order of 7 December 2023 directing status quo. UPSIDA, the lessor authority, said about Rs.44.89 Crores remained unpaid and that sublease deeds could not be executed until dues were cleared and completion certificate obtained. The Court appointed three Committees whose reports, with a report of UPSIDA dated 1 May 2025, found the units unfit for occupation, and the IRP claimed that Rs.74,68,21,277 was transferred from GVCTPL to entities linked to the petitioner's relatives during the moratorium. The petitioner offered Rs. 5 crores, whereas claims of more than 1400 crores were received from about 670 creditors.

Questions before the court

Why the court ruled this way

The condition to settle with the complainants within six to eight months was the foundation of the grant of liberty, and the Court had repeatedly said in its orders of 9 February 2024 and 13 May 2024 that the petitioner must make bona fide efforts for every allottee. The Court relied on the earlier finding of a coordinate Bench in the insolvency appeals, and on the three Committee reports, that construction was not complete and the units were not ready for possession, so the plea that possession was delayed only by UPSIDA's demand failed (paragraphs 58 to 62). The petitioner did not pay the statutory dues of UPSIDA, did not furnish the final list of allottees, and issued allotments through GVCTPL, which was not the authorised lessee, so tripartite sublease deeds could not be executed (paragraphs 67 and 68). He did not comply with settlement agreements giving possession with clear title within 15 months or a refund, and left the Committee's site visit midway (paragraphs 61 and 69 to 71). On similar offences, the Court refrained from making a conclusive finding on siphoning, because quashing proceedings were pending before the Allahabad High Court, but held that transfers of about Rs. 74 crores admitted by the petitioner as commercial advances or repayments, made during the moratorium and the NCLAT's status quo order and without documents, did not show bona fide conduct and were not fully consistent with bail conditions (paragraphs 107 to 121). The Court noted that a two-judge Bench may modify a three-judge Bench's order on clubbing, and any application on clubbing could be made (paragraph 124).

Controlling point

The petitioner did not comply with the conditions of bail imposed on 6 November 2019, so the bail was cancelled and, given the many opportunities, the whole deposit of Rs. 50 crores with accrued interest was forfeited.

Order and next steps

The bail was cancelled and the petitioner was to surrender within one week; he may seek regular bail again after twelve months subject to complying with the orders in the insolvency proceedings; the passport was not to be released by the trial court without leave; Rs. 5 crores with proportionate interest was transmitted to NALSA and the remainder with interest to the IRP for the IBC proceedings; and the Miscellaneous Petitions were allowed and pending applications disposed of.

Practical implications

A promoter who is granted bail on a condition of deposit and settlement with homebuyers should treat it as a condition that must be met in substance, with proof of bona fide efforts and attention to the statutory dues and the state of the project, and should avoid moving funds from companies under moratorium.

Limits of this ruling

Law and judgment source

The linked PDF is a complete public court-copy document. The official court portal is provided for independent verification; a stable judgment-specific official link was not independently established.

Source checked: 2026-10-06 · Judgment paragraphs: paragraphs 1-130 · Later case history: not verified. Verify appeals, stays and subsequent orders before reliance.

This page is informational. Verify the current official court record, subsequent history and applicable law, and obtain professional advice for a specific matter.