Using LDB Data in Container Detention Disputes: Timeline, Handover and Delay Evidence

By Ravi Sisodia · Reviewed by CA Divyanshu Sengar · Updated 5 October 2026

2-minute summary

Current position

For detention, the critical operational period is normally outside the terminal/depot after equipment pickup. LDB movement data can corroborate that timeline, but EIR/depot acceptance, line instructions and the agreed free-time rule remain the core documents for a charge dispute.

Control and evidence map

#Control / evidence requirement
1Extract the detention tariff/free-time terms and container type.
2Capture terminal exit/pickup event, EIR, delivery/warehouse arrival, empty-return attempt and accepted return.
3Record depot appointment/rejection evidence and any line instruction that changed the return location.
4Compare LDB movement timestamps with transporter GPS/FASTag and EIR records.
5Create a charge-day reconciliation and identify days attributable to disputed depot/line constraints.

Worked example

An empty container reaches the nominated depot within free time but is rejected because the depot is full and accepted two days later. The dispute should include the first return attempt, depot rejection, revised instruction and LDB/vehicle trail rather than only the final EIR.

Common mistakes

  1. Using port dwell data as a substitute for empty-container return evidence.
  2. Ignoring the EIR or depot rejection note.
  3. Applying the wrong free-time rule for container type or trade lane.
  4. Failing to document a changed return depot instruction.

Frequently asked questions

Is detention the same as demurrage?

No. The operational and charge periods are different and should be reconciled separately.

Can LDB prove empty return?

It may support movement, but depot/EIR acceptance evidence is usually essential.

What if the depot refused the return?

Preserve the rejection and line instructions and quantify the affected charge days.

What timeline should be built?

Pickup, delivery/unloading, return attempt(s), acceptance and any rerouting instruction.

Official sources

Disclaimer: Educational and informational content only. Apply the current law, instrument, policy/contract and facts before acting; obtain professional advice for material or disputed matters.