The calculator uses EOQ = square root of (2 x annual demand x ordering cost / annual holding cost per unit). Reorder point equals expected demand during lead time plus safety stock. These are planning models, not statutory quantities or supplier commitments.
| Input | Use a defensible measure | Sensitivity risk |
|---|
| Annual demand | Normalised forecast by item and unit of measure. | Seasonality, launches and lost sales can make a single annual average misleading. |
| Ordering cost | Incremental procurement, freight/setup and receiving effort per order. | Do not include costs that do not change with order frequency. |
| Holding cost | Capital, storage, insurance, shrinkage and obsolescence per unit/year. | A low estimate inflates EOQ and inventory exposure. |
| Lead time/safety stock | Observed supplier lead-time distribution and service-level policy. | The simple reorder formula does not calculate statistical safety stock. |
Worked example
Annual demand is 12,000 units, ordering cost Rs 500 and holding cost Rs 24 per unit/year. EOQ is about 707 units. At 365 operating days, 10-day lead time and 100 units safety stock, the simple reorder point is about 429 units. Round for pack size and test storage capacity before issuing a policy.
Exception case
A supplier offers a quantity discount at 1,000 units. Basic EOQ cannot decide the offer by itself. Compare purchase-price savings with additional holding, expiry, working-capital and capacity costs at each price break.
Questions
Why can ordering and holding cost be equal at EOQ? Under the basic assumptions, the minimum occurs where the two relevant annual cost components balance. Can EOQ be used for intermittent demand? The stable-demand model may be poor; use an intermittent-demand and service-level method. Should the result be rounded? Yes, but evaluate pack sizes, minimum order quantities and resulting total cost.
Management-planning model only. Validate demand, lead time, service level, capacity, expiry and supplier terms before changing purchase policy.
Methodology, assumptions and sources
Scope: Computes the Economic Order Quantity (EOQ) — the order size that minimises total inventory cost — and the reorder point, using the classic inventory management formula.
Calculation logic
- EOQ = √((2 × Annual demand × Ordering cost per order) ÷ Holding cost per unit per year).
- Reorder point = (Average daily demand × Lead time in days) + Safety stock (if entered).
- Total annual inventory cost at EOQ = Ordering cost component + Holding cost component, shown to confirm the EOQ minimises total cost.
Inputs and assumptions
- The EOQ formula assumes constant demand, constant lead time, and no quantity discounts — the classical Wilson EOQ model.
- Safety stock, if entered, is added as a fixed buffer and does not itself change the computed EOQ, only the reorder point.
Exclusions and edge cases
- Does not model quantity-discount pricing tiers, perishable/spoilage constraints, or stochastic (variable) demand — those require more advanced inventory models beyond classical EOQ.
- This is a planning estimate; actual reorder decisions should also account for supplier minimum order quantities and storage constraints.
Sources
No external regulatory source applies — this is a general financial formula, not a statutory computation.
Review status: reviewed and approved by CA Nikhil Gupta on 18 July 2026.